How long will it take to allocate a site?
Once a selection procedure has been initiated, prospective tenants generally have 6-8 weeks to express their interest and submit the information required for participation. This is followed within 3-4 months by an internal administrative review and assessment of the information submitted, which is then presented to the Economic Committee in a City Council presentation. The city council decides on the administration's proposal on this basis.
When can a company start planning and submit a building application if the space is available?
Once the decision has been made, all applicants will be notified whether the application was successful or not. The successful company can then start the contract negotiations, which are conducted by the municipal department. At the same time, the company can start planning and prepare a building application (Bauantrag). As soon as a building permit (Baugenehmigung) has been granted, the project can begin on the commercial property.